The Bonding Company Checklist for Public Works Projects

Public owners do not forgive sloppy bonding. They cannot. Taxpayer money is at stake, schedules tie to funding cycles, and political scrutiny lands on every delay. If you are a contractor, broker, or project owner navigating a public works job, the bonding company will be your quiet partner from prequalification through final completion, sometimes for years after. The right preparation keeps surety underwriters confident, bids valid, and projects liquid. The wrong move can torpedo a low bid in an hour.

What follows is the field-tested checklist I use when preparing a file for a public works project, along with the reasoning behind each item. It is written with the perspective of someone who has sat at the table with owners, read through dog-eared general conditions, and watched claims unfold when small documentation gaps turned into big financial problems. Match your situation to these steps and you will anticipate most of the questions a bonding company will ask, in the order they ask them.

Why bonding is different on public work

Public owners demand performance and payment bonds because statutes require them. Miller Act at the federal level and Little Understanding Axcess Surety bonds Miller Acts in the states set thresholds and standard forms. Public entities cannot place liens on their own property, so the payment bond becomes the lifeline for subs and suppliers. The performance bond protects the owner if the prime falters. That legal backdrop changes how a bonding company underwrites risk.

On private work, surety underwriters often negotiate bond forms or accept bespoke language. On public work, forms are frequently dictated. You may face AIA A312 or government agency forms that shift risk in subtle ways. Rates might look similar, but underwriting scrutiny is sharper. Expect your bonding company to dive into your backlog, working capital, and staffing plan before issuing anything beyond a bid bond.

Pre-bid: qualify first, then chase the job

I have seen good contractors lose bid opportunities because they treated bonding as an afterthought. Prequalification is not a paperwork drill, it is an underwriting decision that can affect your whole year of work. If the project value would push your single job limit or aggregate program, you need to engage your agent and bonding company early, sometimes weeks before the bid date. That is especially true for seasonal surges like school modernization work packed into the summer.

Start by aligning the project’s risk profile with your company’s demonstrated strengths. If your past two years were heavy in site utility work and you now want to prime a structural steel and curtain wall package, the bonding company will want to understand who on your team has actually delivered that scope at scale. If the answer is “we will hire it out,” then you need to show subletters, prequal files, and cost controls that avoid margin erosion.

The bonding company’s lens on capacity

Surety underwriting hinges on the three Cs: character, capacity, and capital. Character is the trust you have built with the bonding company over time. Capital is what your balance sheet says you can absorb when things go sideways. Capacity is your ability to control schedule, subcontractors, and scope on the specific job. When a project is public, capacity includes fluency with prevailing wage reporting, certified payroll, prompt pay statutes, DBE or MBE participation, and change order procedures that can stretch for months.

Underwriters will look for lagging indicators first, then leading indicators. Backlog gross profit fades on under-billed jobs, and strained working capital shows up in spiking payables. If your WIP shows more than 20 to 25 percent of jobs with costs exceeding billings by wide margins without clear explanations, expect questions. If retainage is sitting past statute or owner contract terms, the bonding company will want to know why. The earlier you give them a narrative with evidence, the easier the conversation.

The core documents that win approvals

Every bonding company has its own flavors, but nearly all require a standard set. Assemble it cleanly, and you remove friction.

    Most recent fiscal year-end CPA financial statements, with at least a review level for mid-sized firms and an audit for larger programs. A compilation can work for small contractors, but it will cap your program. Current interim financial statements, no older than 90 days at the time of bid, with job schedules that tie out to the balance sheet and income statement. Detailed work-in-progress and completed contracts schedules, showing contract value, cost to date, estimate at completion, billings, and gross profit to date. Bank line of credit terms and compliance, including any borrowing base calculations and covenants, plus a six-month snapshot of availability. Project-specific information: bid date, owner, form of contract, liquidated damages, bond forms, engineer’s estimate, scope narrative, jobsite location, duration, and construction schedule.

If the file is thin in one area, strengthen another. When your interim statements are late, bring in third party references, demonstrate cash management discipline, and submit a documented staffing plan. Underwriters reward clarity as much as they reward numbers.

Reading the owner’s bond form like a claims person

Your bonding company will scrutinize the bond form and the underlying contract as if they had to litigate them tomorrow. This is not cynicism, it is how claims are avoided. Watch for these provisions that commonly trigger pushback from underwriters.

Some public owners modify standard bond forms to expand the surety’s obligations beyond the contractor’s. If a bond says “Surety shall complete the work upon default, regardless of defenses,” underwriters will ask for riders or exceptions. Pay attention to notice requirements too. If the owner can declare default without a cure period or without written notice to the surety, your bonding company may condition approval on negotiated changes.

Payment bonds should align with the project’s tiered payment environment. If the jurisdiction allows fourth-tier claimants to make demands on the bond, the bonding company will price and underwrite accordingly. Not every market sees this, but a public university system or a transit authority may have wider coverage expectations. Know your local statutes and make sure your bonding company does too.

The bid bond trap that snags good contractors

Bid bonds look simple. Post a 5 or 10 percent guarantee, deliver the performance and payment bonds if awarded. The trap lies in short fuses. Public owners often require performance and payment bonds within 3 to 10 business days after award. If the contract price escalates through alternate acceptance or unit-price extensions, your bonding company must be ready for a larger penalty than the base bid. Clarify your alternate strategy with the underwriter in advance. If you plan to be aggressive on an alternate to win, disclose it and confirm the single job limit can absorb the potential award.

There is also the “no substitution” clause problem. Some owners require bonds from a specific bonding company list or a Treasury-listed surety. If your current surety is not on that list, you may have a valid bid that you cannot convert into a contract. Confirm eligibility early. It is a bad day when a low bid evaporates because a clerk rejects the surety on technical grounds.

The real cost of bonding, and how to manage it

Bond premium is a small slice of total project cost, often 0.6 to 1.8 percent for performance and payment bonds combined, scaled by size and credit. Public jobs with tight completion windows or complex environmental scopes may price higher. Your bonding company cannot mark up rates beyond filed tariffs in most states, but schedules allow for underwriting credits based on financial strength and past performance. Treat your surety like a partner, not a commodity, and you can often earn rate relief over time.

What really moves cost is not the rate but the loss experience. If a job goes bad and the surety pays, your future rates trend up and your capacity trends down. On the other hand, when you communicate early about emerging issues and avoid formal declarations of default, you preserve both your relationship and your cost structure.

Building your internal bond file before the bid

A public works file that moves smoothly through a bonding company has two qualities: it reads like a coherent story, and it answers the questions that would otherwise require follow-up. I coach teams to assemble their internal file with a short narrative on the job, a cash flow rough-in, and a staffing matrix with named individuals and commitment levels. Two pages of well-organized narrative can save a week of back-and-forth.

Here is a compact checklist I use on every public job. It fits on a single page and covers what underwriters actually check first.

    Owner and delivery method, including statute or agency protocol that governs bonds. Form of contract and bond forms, with flagged clauses that deviate from industry standards. Bid date, anticipated award date, and required bond delivery window, including any alternates. Detailed WIP and financials tied to the same date, with any large swings explained. Project plan: schedule milestones, labor plan, key subs, and cash flow assumptions for the first 90 days.

If you are a subcontractor seeking a bond on a public prime job, mirror this list. Add the prime’s payment history and owner funding certainty. The bonding company wants to know whether payment will flow downstream promptly, because your cash is more fragile than a prime’s.

Funding certainty and the politics of public money

Unlike private developers, public owners fund projects through appropriations, bonds, grants, or dedicated tax streams. That can be both comforting and risky. Comforting because the money is theoretically there. Risky because disbursement can be gated by board approvals or fiscal year boundaries. Your bonding company will ask how funding is structured. If a school board must approve each change order, the cash flow on your extras may lag 60 to 120 days. That has to be reflected in your working capital plan.

A simple example: a contractor started a $14 million municipal pool renovation with a front-loaded demo and sitework schedule. The city funded base scope, but extras required council votes. When they uncovered asbestos not shown in the surveys, the change order took two meetings and 45 days. The contractor’s cash burn doubled in that period. The bonding company did not panic because they had seen the cash plan and knew the line of credit had headroom. That coordination saved the job from a liquidity scare.

Compliance is not paperwork, it is risk control

Public work comes with prevailing wage, certified payroll, apprenticeship ratios, and prompt payment requirements. Some jurisdictions require electronic payroll submission weekly through state portals. Non-compliance brings penalties and, more importantly, it invites claims from workers and subs that can land on the payment bond. Your bonding company will want confirmation that your field and back office teams can meet these requirements without drama.

I advise clients to run a dry run of certified payrolls if they have not done one in over a year. It keeps everyone honest. Verify that fringe benefits are calculated correctly and applied consistently to base rates. Validate that apprentice hours line up with ratios. In a claims file I reviewed, a small contractor lost nearly 4 points of margin because they misapplied fringe credits, then paid penalties and legal fees. The bonding company stayed on the program, but the firm’s capacity shrank for a year. This is avoidable with discipline.

Subcontractor risk on public work

Even well-capitalized primes fail when subs fail. On public jobs, you usually cannot handpick every sub without prequalification, and sometimes you inherit outreach goals for DBE, MBE, or WBE participation that create constraints. Underwriters know this. They will ask how you vet subs and what controls you use to avoid front-loading payments.

Practical measures carry weight. Joint check agreements, clear pay-when-paid clauses that comply with state law, and incremental scopes for shaky subs reduce exposure. Bonded subcontracts can make sense on large or specialized trades, but do not assume a bonding company loves them in every case. A bonded sub has its own surety, which can complicate claims coordination. Use bonded subs for structural, envelope, or high-risk trades where replacement would damage schedule, and pair that with back-up subs quietly queued.

The claim the bonding company actually fears

It is not the straightforward default. That is painful but manageable. The fear is the slow bleed, the job that looks fine in monthly reports, then suddenly requires a cash infusion when the retainage is still trapped and the owner contests a bundle of change orders. I have watched experienced teams avoid this by keeping a running ledger of disputed items with contemporaneous documentation. They price and submit early, even when the owner is not ready to evaluate, and they capture field directives in signed T&Ms with photos and foreman notes.

Your bonding company cannot do that work for you, but they will relax when they see your process. If you notify them that a large unresolved change order is now three months old and has real cost weight, they can help escalate conversations. They value no-surprise relationships. So do owners.

Practical timelines that keep bonding on schedule

Work backward from the bid date. If the project is within your current surety program limits and no unusual terms exist, assembling the file can take a couple of days. If the job stretches your limit or contains hard clauses, give it ten business days. For audited financials or year-end renewals, some bonding companies need two to three weeks to recalibrate your limits.

After award, the execution of bonds depends on obtaining final contracts and power of attorney verification. Public owners often require original seals or wet ink signatures and Treasury-listed sureties. Plan for overnight shipments and the potential for an attorney-in-fact to be temporarily unavailable. I keep a shortlist of alternate signatories with valid powers of attorney so a single sick day does not delay bond delivery.

How owners and agencies can streamline bonding

Public owners sometimes view the bonding company as a hurdle. The surety is more like a quiet auditor of contractor capacity. When owners want more competition and fewer bid withdrawals, small operational decisions help. Clear and early issuance of final bond forms lets underwriters vet terms before bid day. Preserving standard AIA or consensus surety language reduces negotiation cycles. Listing acceptable sureties as Treasury-listed and not narrower maintains fairness without choking the field.

Owners can also time awards to avoid impossible bond delivery windows. If you award on a Friday at 4 p.m. and require bonds by Monday morning, you are asking for a scramble that should be unnecessary. A three to five business day window satisfies administrative needs and respects logistics.

image

Navigating edge cases

Edge cases define the craft of bonding on public work. A few that recur:

    Unit price jobs with unknown quantities. Underwriters look for realistic production rates and contingencies. If your estimate banked on perfect productivity, expect questions. Bring crew-hour benchmarks from recent similar work, especially if soils or traffic control complicate rates. Joint ventures. The bonding company will require a JV agreement, clear allocation of profit and loss, and cross-corporate guarantees. They will assess whether the JV is additive or a bandage covering weak capacity in both firms. Multi-prime coordination. When the owner holds separate contracts for trades, the risk of interface delays rises. Your bonding company will gauge how you manage dependencies outside your control. Document meeting protocols, RFI gateways, and float protection. Fast-track schedules. Accelerated work raises overtime burn and supply chain fragility. Underwriters want vendor commitments with lead times and escalation handling. A letter from a key supplier can tilt a decision toward approval.

Closeout and the tail on the bond

Too many teams celebrate substantial completion and forget how much risk remains in closeout. Public owners can Axcess Surety hold retainage until paperwork is perfect. The bonding company monitors the tail because warranty work and claims often surface months after punch list. Structure your closeout plan early: O&M manuals in correct formats, as-builts verified by engineering, training sessions scheduled before staff turnover, and a warranty response protocol with named contacts.

A contractor I know cut their closeout cycle by half when they pushed submittal logs to 100 percent before final inspections and staged training with owner personnel on mutually agreed dates. The bonding company noticed. The next year, they raised single job capacity by 25 percent without a rate increase. Consistent closeout performance is a real underwriting metric, even if it is not printed on any schedule.

The contractor’s relationship with the bonding company

The best relationships look like steady, calm conversations. You send clean financials quarterly, call when a job hiccup appears, and do not try to hide problems. In return, the bonding company leans in when you find a growth opportunity. They waive a minor covenant trip when they see a plan to cure, or they stretch a single job limit for a strategic project. That reciprocity is earned.

I remind growing contractors that a bonding company is not a bank, but it thinks like one about risk. Treat forecasts as promises, not hopes. Use measured language about contingencies. Share the ugly as soon as you spot it, paired with actions and dates. It builds credibility, and credibility is a currency you can spend on bid day.

A field-ready one-page summary to keep near your desk

Sometimes you just need a quick reference before the call with your agent. Keep this second checklist handy when a public job appears. It helps you frame the conversation with your bonding company in five minutes.

    Scope and risk snapshot: what is unique, what is familiar, where can it go wrong. People and partners: superintendent, PM, scheduler, critical subs, and alternates. Money map: first-90-day cash flow, line availability, retainage and change order timing. Paper trail: bond forms, contract terms, notice provisions, wage and reporting requirements. Decision dates: bid, expected award, NTP, long-lead releases, and bond delivery deadline.

If you can speak to those five buckets without rummaging through files, you sound like a contractor who controls risk, not one who reacts to it. That tone sets the table for a smooth approval.

Final thoughts from the claims side of the table

Most bond claims on public jobs begin months before anyone calls the bonding company. They start with underbilled work, slow documentation, and payment friction that nobody escalated. The remedy is not complicated. Put structure around your paperwork. Keep honest WIP schedules. Teach your field to capture change conditions with photos and short, dated notes. Treat certified payroll as a production metric, not a compliance chore. Call your agent when a risk crosses a threshold that you would not want to explain after the fact.

A bonding company will never build the project for you, but the best ones see around corners. When you bring them a file that reflects discipline, they will back you when the stakes rise. On public works, where forms and statutes compress discretion, that vote of confidence is often the difference between landing the job and watching it go to the next bidder.